Here’s an action plan with a timeline for setting up and configuring a Meraki Client VPN:


Phase 1: Pre-Setup Planning

Objective: Assess the network and determine VPN requirements.

Tasks:

  1. Review Network Topology:
    • Assess subnets, IP ranges, and identify internal resources that need VPN access.
    • Time: 0.5 day
  2. Define VPN Subnet and DNS:
    • Select an appropriate VPN IP range and DNS servers.
    • Time: 0.5 day
  3. Select Authentication Method:
    • Decide between Meraki Cloud, AD, or RADIUS authentication.
    • Time: 0.5 day
  4. Ensure VPN Compatibility:
    • Verify compatibility with user devices (Windows, macOS, iOS, Android).
    • Time: 0.5 day

Deliverables:

Total Time: 1–2 days


Phase 2: Meraki Dashboard Configuration

Objective: Configure the client VPN on the Meraki dashboard.

Tasks:

  1. Login to Meraki Dashboard:
    • Access the dashboard with admin credentials.
    • Time: 0.5 day
  2. Enable Client VPN:
    • Enable Client VPN and configure subnet, DNS, and shared secret.
    • Time: 0.5 day
  3. Configure Authentication:
    • Set up Meraki Cloud, AD, or RADIUS authentication.
    • Time: 1 day
  4. Set Firewall Rules:
    • Configure firewall rules to control VPN user access to internal network resources.
    • Time: 1 day

Deliverables:

Total Time: 2–3 days


Phase 3: Client Device Setup

Objective: Set up VPN configurations on user devices.

Tasks:

  1. Distribute VPN Setup Instructions:
    • Provide users with instructions on configuring the VPN on their devices.
    • Time: 0.5 day
  2. Configure VPN on Windows, macOS, iOS, and Android:
    • Provide support for users setting up their devices and handle troubleshooting.
    • Time: 2–3 days, depending on the number of users.

Deliverables:

Total Time: 2–3 days


Phase 4: Testing and Validation

Objective: Test the VPN functionality and ensure proper access.

Tasks:

  1. Test VPN Access:
    • Test connections from different device types to verify the VPN setup.
    • Time: 1 day
  2. Check Logs for Issues:
    • Review Meraki dashboard logs to check for errors or authentication problems.
    • Time: 0.5 day
  3. Verify Network Access:
    • Ensure that VPN users can access the internal network resources as defined.
    • Time: 0.5 day

Deliverables:

Total Time: 1–2 days


Overall Timeline: 6–10 days


Summary of Deliverables:

This timeline ensures thorough planning, configuration, testing, and user support, minimizing the risk of errors and ensuring a smooth setup process.